September 7, 2021 Three Week Look Ahead
August 25, 2021 Three Week Look Ahead
August 4, 2021 Three Week Look Ahead
July 13, 2021 Three Week Look Ahead
June 29, 2021 Three Week Look Ahead
Notificación en español
The 1st Street Relief Sewer Project will replace two existing operating underground sanitary sewer pipelines by open cut excavation. Sanitary Sewer Service to Homes and Businesses within the Project Boundaries will be maintained throughout the course of construction. The Project was Designed by V.W. Housen Associates. D’Arcy & Harty are the General Contractors performing the work. Veolia North American CPM will be providing Construction Management.
The General Vicinity of Project Boundaries are Nevin Ave (North); Cutting Blvd (South); Collins St./Chanslor Ct. (West); 6th Street (East). See project map
The project consists of:
+/- 3,743 LF of Open Cut replacement of 6” Sewer Pipeline (being upsized to 8”)
+/- 1,696 LF of Open Cut replacement of 8” Sewer Pipeline
+/- 631 LF of Open Cut replacement of 10” Sewer Pipeline
+/- 125 LF of Open Cut replacement of 18” Sewer Pipeline.
Additionally:
+/- 865 LF of Pipe Bursting of 8” & 10” Sewer Pipelines
+/- 392 LF of Point Repairs on 6”, 8” & 18” Sewer Pipelines
Questions? Contact Jacqueline Majors 925-949-6196 jacqueline@majorsandassociates.com