This project intends to complete Carlson Blvd Crosstown Connection Improvements Project from Broadway to Tehama Ave by installing bicycle lanes, pedestrian ramp facilities, bus shelter connections for future make-ready installation, asphalt paving, sidewalk and root repairs, signing and striping, and streetlight study. Broadway to Tehama will feature Class II bike lanes, and class IV bike lanes where feasible. This corridor will be upgraded to enhance safety and improve traffic flow along Carlson Boulevard. The new bikeway will connect existing bike lanes on Carlson Boulevard at San Pablo Avenue in El Cerrito north to Broadway, near Richmond Civic Center.
The Bayview to BART effort is currently in planning and will create a safe and comfortable walking and biking route connecting the Del Norte BART station to the San Francisco Bay Trail. Construction is tentatively scheduled to begin Spring 2027 and be completed by Spring of 2028. It will entail Class II bike lanes on Potrero Ave as well as build Class IV protected bike lanes on the Bayview Ave overpass over I-580, curb ramps, sidewalk repairs, and pavement rehabilitation. Final limits are in active discussion with Caltrans.
23035 Traffic Calming Program
Within Project Limits: Rectangular Rapid Flashing Beacons have been installed at: Carlson and Carl, Carlson and Tehama.
Within Corridor: Rectangular Rapid Flashing Beacons have been installed at: Carlson & Sutter, Carlson & Shasta
Improve at grade pedestrian and bicycle crossing with railway tracks. Safety and visibility improvements will be implemented within the vicinity of this intersection and railway.
Cutting Blvd Transit Improvement Project - PM AC Transit
Traffic Safety improvements study and implementation on Carlson between Tehama and San Jose.
Streetlighting Improvements
Median Beautification
Bus Shelters (Grant opportunity)
PROJECT TIMELINE
February 2026
Completed design.
March 2026
Bid Advertise.
May 2026
Bid Award.
July 2026
Construction Start.
July 2027
Construction End.
ADDITIONAL INFORMATION
Project Manager: Mike Owyang Project Phase: Design Project Category: Transportation Project Location: Carlson Boulevard between 22nd Street and Tehama Avenue, 22nd St between Nevin Avenue to Carlson Avenue, 24th Street between Nevin Avenue and Broadway Avenue, Broadway Avenue between 24th Street and Carlson Boulevard Neighborhood: Belding Woods City Council District: 3 City Council Priority: Quality of Life Community Meeting Presentation