This project will improve traffic safety for all users. The project will include installation of pedestrian pathway improvements, warning devices, railroad safety devices, new traffic signals, ADA ramps, domes, pedestrian gates, signing and striping.
This work will include coordination with the Union Pacific Railroad, California Public Utilities Commission, Caltrans, and Capitol Corridor Joint Powers Authority.
PROJECT TIMELINE
June 2026
Design complete.
December 2026
UPRR, CPUC, CCJPA Coordination
April 2027
Bid & Award.
November 2027
Construction Start.
May 2028
Construction End.
ADDITIONAL INFORMATION
Project Manager: Mike Owyang Project Phase: Design Project Category: Transportation Project Location: Cutting Boulevard @ Carlson Boulevard Neighborhood: Pullman, Cortez/Stege City Council District: 3